Gurgaon-Palwal Transmission Limited (GPTL)

GPTL – Gurgaon-Palwal Transmission Limited  Image

GPTL was incorporated on October 26, 2015. GPTL entered into a TSA on March 4, 2016. The GPTL project was awarded by the Ministry of Power on March 17, 2016 for a 35-year period from the scheduled commercial operation date of the GPTL project, on a BOOM basis. We acquired 49% of GPTL (with 100% economic interest) from SGL4 in August, 2020.

Details of GPTL’s transmission lines, substations and line bays are set forth as follows:

Transmission Line / Substations Route Length (ckms) Specifications Commission Date Expiry of TSA Term Contribution to Total Tariff
Aligarh - Prithala99400 kV D/C HTLS line August 06, 2019July 205417.5%
Prithala – Kadarpur55400 kV D/C HTLS lineDecember 7, 2019July 20548.5%
Kadarpur-Sohna Road22400 kV D/C HTLS lineMarch 21, 2020July 20541.3%
LILO of Gurgaon Manesar2400 kV D/C Quad lineMarch 13, 2020July 20540.75%
Neemrana – Dhonanda93400 kV D/C HTLS lineFebruary 25, 2019July 205412.55%
Kadarpur substation-400/220 kV, 2 x 500 MVADecember 11, 2019July 205419.3%
Sohna Road substation-400/220 kV, 2 x 500 MVAApril 13, 2020July 205420%
Prithala substation-400/220 kV, 2 x 500 MVAAugust 8, 2019(1)July 205419.3%
Dhonanda substation-Two 400 kV line baysFebruary 25, 2019July 20540.8%

(1) Deemed commission date.

The average quarterly availability of GPTL since commissioning is set forth in the table below:

*Quarterly data is calculated as an average of three months data, based on the monthly availability certificates.
*Certain data post September 2020 are based on estimates.